Nov 11 (Reuters) - TransCanada Corp TRP.TO :
* Awarded contract to build US$500 million natural gas Tuxpan Tula pipeline in
Mexico
* Says anticipates an in-service date in the fourth quarter of 2017
* Says construction is expected to start in 2016
* Says pipeline will be approximately 250 kilometres (155 miles) long and have
contracted capacity of 886 million cubic feet a day (mmcf/d)
* Expects to invest about $500 million in pipeline and anticipates an
in-service date in the fourth quarter of 2017
* Source text for Eikon urn:newsml:reuters.com:*:nMKW0QPHha
* Further company coverage TRP.TO