U.S. wants more from ETP before Rover natgas pipe can start up

Published 2017-07-12, 04:27 p/m
© Reuters.  U.S. wants more from ETP before Rover natgas pipe can start up
RRC
-
NG
-
EQT
-
GPORQ
-

July 12 (Reuters) - U.S. energy regulators on Wednesday gave Energy Transfer Partners LP ETP.N a list of tasks to complete before the Rover natural gas pipeline can enter service.

The $4.2 billion Rover project from Pennsylvania to Ontario is the biggest gas pipeline under construction in the United States.

ETP has long said it expects the first phase of Rover to enter service in late July with the second phase by Nov. 1. energy analysts, however, have said an order by the U.S. Federal Energy Regulatory Commission (FERC) on May 10 banning ETP from new horizontal directional drilling under waterways and roads after a spill in Ohio could cause delays.

ETP spilled about two million gallons of drilling fluid, a clay and water mix, into Tuscarawas River wetlands in Ohio in April.

FERC said in a letter it will continue to ban ETP from new horizontal drilling until it gains "at least a preliminary understanding of the underlying causes for the presence of petroleum hydrocarbons" in the fluid that spilled into the Tuscarawas wetlands. said it did not approve the use of hydrocarbons in the drilling fluid for Rover.

"I am concerned that the lack of availability of Rover's personnel and its contractors' personnel is delaying our ability to determine the relevant facts," Terry Turpin, director of FERC's Office of Energy Projects said in the letter.

FERC also said a third party contractor helping the commission put together a plan to prevent further inadvertent releases was still working on that plan.

3rd party Ad. Not an offer or recommendation by Investing.com. See disclosure here or remove ads .

In addition, FERC wants ETP to develop a remediation plan for the Tuscarawas River wetland and remove and dispose of drilling fluids to a site approved of by Ohio's environmental regulators, among other things.

Earlier this week, the Ohio Environmental Protection Agency asked the state's attorney general to pursue civil penalties against ETP for environmental violations during the Rover construction.

Once it enters service, the pipeline will move up to 3.25 billion cubic feet per day of gas from the Marcellus and Utica shale fields in Pennsylvania, Ohio and West Virginia to customers in Ohio, Michigan, Ontario and elsewhere.

One bcf of gas is enough to power about 5 million U.S. homes.

Analysts expect several energy companies to increase gas production once Rover enters service to fill the pipe, including Antero Resources Corp AR.N , Eclipse Resources Corp ECR.N , EQT Corp (NYSE:EQT) EQT.N , Gulfport Energy Corp GPOR.O , Rice Energy Inc RICE.N , Range Resources Corp (NYSE:RRC) RRC.N and Southwestern Energy Co SWN.N .

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.