U.S. FERC orders ETP to halt one Rover natgas pipeline drill, delays seen

Published 2018-01-25, 03:58 p/m
© Reuters.  U.S. FERC orders ETP to halt one Rover natgas pipeline drill, delays seen
RRC
-
NG
-
EQT
-

Jan 25 (Reuters) - U.S. federal energy regulators told Energy Transfer Partners ETP.N to consider alternatives to get its Rover natural gas pipeline to cross the Tuscarawas River in Ohio, which an analyst said could delay completion of the project.

After a few weeks of drilling under the Tuscarawas, the U.S. Federal Energy Regulatory Commission (FERC) on Wednesday ordered ETP to cease work at the site.

ETP planned to run two pipes under the Tuscarawas. One is already in service and has over 1 billion cubic feet per day (bcfd) of natural gas flowing through it.

But ETP has run into a difficult rock formation on the drill for the second pipe and has reportedly already lost about 200,000 gallons of drilling fluid down the hole, according to a letter from the Ohio Environmental Protection Agency, which for weeks has been urging FERC to stop ETP's work at the site. drilling fluid, which is a mix of clay and water, has not returned to the surface, according to the FERC filing.

FERC ordered Rover to provide information about the feasibility of completing the current drilling, finding another location to cross under the river or go with just one pipeline under the river.

The company has said it expects to finish Rover by the end of the current quarter. this time, we do not anticipate a change to that in service date," ETP spokeswoman Alexis Daniel said in an email after the company received the FERC order. She said ETP continues to work on the rest of the pipeline.

Analysts, however, think the project will likely be delayed.

"At this point, we don't think it will be done at the end of the first quarter," said Matt Lewis, director of financial analysis at energy research firm East Daley Capital in Centennial, Colorado.

"I don't see this as a huge delay. I figure they will find a way to solve this issue," Lewis said, noting ETP would likely complete the project in the second or possibly the third quarter.

Once finished, the $4.2 billion Rover will carry up to 3.25 bcfd from the Marcellus and Utica shale fields in Pennsylvania, Ohio and West Virginia to the U.S. Midwest and Ontario in Canada.

One bcfd of natural gas can supply about five million U.S. homes.

Major producers signed up to use Rover include units of privately-held Ascent Resources, Antero Resources AR.N , Range Resources (NYSE:RRC) RRC.N , Southwestern Energy SWN.N , Eclipse Resources ECR.N and EQT Corp (NYSE:EQT) EQT.N .

<^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ FACTBOX-U.S. new natural gas pipeline projects

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2025 - Fusion Media Limited. All Rights Reserved.