British Columbia mega dam behind schedule, over budget -regulator

Published 2017-11-01, 02:31 p/m
British Columbia mega dam behind schedule, over budget -regulator
ANA
-
ACOx
-
ARE
-
005930
-
028260
-

VANCOUVER, Nov 1 (Reuters) - A C$9 billion ($7 billion) hydroelectric dam under construction in British Columbia is over budget and a year behind schedule, the province's power regulator said on Wednesday but declined to recommend whether the project should go ahead or be scrapped.

The Site C dam project will flood more than 5,000 hectares (19 square miles) of land, the equivalent of about 5,000 rugby fields, spurring opposition from local farmers and indigenous groups.

The British Columbia Utilities Commission said in a review that the least attractive option was to suspend and restart the Site C project, as that could add billions to the final costs.

British Columbia's former Liberal government approved the project in 2014, saying it would help meet a surge in electricity needs over the next 20 years. It did not ask the regulator for a review.

The province's new NDP government, which ousted the Liberals earlier this year, made a campaign promise to get the regulator's view.

The report said the Liberal government's assumption of future power needs were optimistic and warned that "combined with a continued glut in North American energy markets, this could make it increasingly difficult to sell Site C surplus energy."

Alternative energy sources such as wind and geothermal could result in lower power costs than Site C, it said.

The NDP government is expected to make a final decision on the dam by year-end.

Companies from around the world are involved in the construction. Peace River Hydro Partners, jointly owned by Acciona SA ANA.MC and Samsung (KS:005930) C&T 028260.KS , was awarded the C$1.75 billion contract for civil works, and is bidding for the generating station and spillway contract. Canada's Aecon ARE.TO is part of a joint venture also bidding on a generating station and spillway contract.

Canada's Atco ACOx.TO was awarded an 8-year, C$470 million contract for worker accommodations, while privately held German company Voith Hydro won the C$470 million contract for turbines and generators.

($1 = 1.2873 Canadian dollars)

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2025 - Fusion Media Limited. All Rights Reserved.