Enbridge's Line 3 oil pipeline upgrade challenged by Minnesota govt

Published 2017-09-11, 11:18 p/m
© Reuters.  Enbridge's Line 3 oil pipeline upgrade challenged by Minnesota govt
CL
-
ENB
-

CALGARY, Alberta, Sept 11 (Reuters) - Enbridge Inc's ENB.TO ENB.N upgrade of its Line 3 crude oil pipeline hit an obstacle on Monday after the U.S. state of Minnesota told a regulatory committee that it has no need for the project, and that the existing pipe should be shut.

The testimony by Minnesota's Department of Commerce is the latest challenge against the C$8.2 billion ($6.52 billion) project through the state, which faces fierce opposition from environmentalists and aboriginal groups.

The Minnesota Public Utilities Commission, which heard the testimony, is expected to make a final ruling next year and has to issue a certificate of need before Enbridge, North America's largest energy infrastructure company, can start construction in the state.

"The Department of Commerce (DOC) opinion is only one view, which we and other energy consumers will respond to in detail," said Calgary, Alberta-based Enbridge on Monday.

"We disagree ... as do other shippers and consumers of oil in Minnesota and the U.S. Midwest, as outlined in other testimony filed today substantiating the need for the project," Enbridge said.

The Line 3 replacement project from Hardisty, Alberta, to Superior, Wisconsin, doubles the capacity of the existing line to 760,000 barrels per day and is the largest project in Enbridge's history, according to the company.

Citing expert analysis, Minnesota's Department of Commerce said refineries in the state and the upper Midwest "are not short of physical supplies of crude oil, and that they have little room to increase total crude runs."

"Minnesota demand for refined products appears unlikely to increase in the long term," the department said.

The department added Enbridge had expanded another pipeline in the region, Line 67, and that other existing and proposed energy infrastructure would be viable alternatives for Line 3, which the state can do without.

Enbridge said last month the Line 3 replacement project will cost 9 percent more than its previous forecast, citing in part regulatory delays. in Canada's oil heartland of Alberta, whose landlocked crude trades at a discount to the West Texas Intermediate benchmark, say they need additional export capacity to attain higher prices.

($1 = 1.2578 Canadian dollars)

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2025 - Fusion Media Limited. All Rights Reserved.