Calibre Mining Corp. (CXB.TO) held its first-quarter earnings call for 2024, providing updates on the development of the Valentine Gold Mine. The company announced that it had met its gold production target for the quarter, delivering 61,700 ounces. The Valentine Gold Mine project is making steady progress, currently 64% complete with detailed engineering nearly finished at 98%. Despite the significant progress, the initial capital costs for the project have risen to $653 million. However, the company assured that the mine is fully funded and on track to produce its first gold in the third quarter of 2025.
Key Takeaways
- Calibre Mining Corp. delivered 61,700 ounces of gold in Q1 2024, aligning with expectations.
- The Valentine Gold Mine is 64% complete, with detailed engineering at 98%.
- Initial capital costs have increased to $653 million, with $279 million remaining to be spent.
- The mine is fully funded, with the first gold pour scheduled for Q3 2025.
- The company has filled all major positions for the operation's leadership team, many of whom are relocating to Newfoundland and Labrador.
- Exploration efforts have identified high-priority drill targets, and recent discoveries near the Leprechaun pit may enhance the mine plan.
- Federal permits for the Berry project are progressing without significant delays, with a start date in early Q3 2025.
Company Outlook
- The company is focused on completing the Valentine Gold Mine and moving towards the operational phase in the Middle East.
- Recruitment efforts have been successful, with key leadership roles filled.
- Partnerships with RCC will facilitate a smooth transition from project to operations phase.
Bearish Highlights
- The increase in initial capital costs to $653 million may pose concerns for stakeholders.
Bullish Highlights
- The leadership team is strong, and labor shortages have not impacted the recruitment of top talent.
- There is potential for increased throughput to 3 million tonnes per year, which could enhance production profiles.
- Optimizations in the crushing and grinding circuit may lead to production exceeding initial estimates.
- New discoveries could be mined early in the mine's life, adding to the production profile.
Misses
- Further drilling is required to explore the southwest area outside the Leprechaun pit to confirm and expand resources.
Q&A Highlights
- The company addressed the cost of pre-commissioning and commissioning activities, estimated between $9 million to $10 million in Canadian dollars.
- Management expressed confidence in the federal permit process for the Berry project and the anticipated start date.
- The potential for early mining of new discoveries near the Leprechaun pit was discussed, pending further exploration and assay results.
Calibre Mining Corp.'s earnings call highlighted the company's commitment to advancing the Valentine Gold Mine project, with a clear focus on completing construction, securing necessary permits, and optimizing production. The company remains optimistic about its exploration efforts and the ability to attract a skilled workforce. With the first gold pour expected in the third quarter of 2025, Calibre Mining Corp. is positioning itself for a significant presence in the gold mining industry.
Full transcript - None (CXBMF) Q1 2024:
Operator: Hello, and welcome to the Calibre Mining Corp. 2024 Quarter One Conference Call and Valentine Gold Mine Update. All participants will be in listen-only mode. [Operator Instructions] After today’s presentation, there will be an opportunity to ask questions. [Operator Instructions] As a reminder, this conference is being recorded. I would now like to hand the call to Ryan King. Please go ahead.
Ryan King: Thank you, operator. Good morning, everyone, and thank you for taking the time to join the call this morning. Before we commence, I'd like to direct everyone to the forward-looking statements on Slide 2. Our remarks and answers to your questions today may contain forward-looking information about the company's future performance. Although, management believes that our forward-looking statements are based on fair and reasonable assumptions. Actual results may turn out to be different from these forward-looking statements. For a complete discussion of the risks, uncertainties and factors which may lead to actual operating and financial results being different from the estimates contained in our forward-looking statements. Please refer to the Q1 2024 MD&A and consolidated financial statements available on our website as well as on SEDAR+. And finally, all figures are in U.S. dollars unless otherwise stated. Present today with me on the call are Darren Hall, President and Chief Executive Officer; David Splett, Senior Vice President and Chief Financial Officer; and Tom Gallo, Senior Vice President of Growth. We will be providing comments on first quarter 2024 results and Valentine Gold Mine update following yesterday's news releases, we will discuss capital costs and project updates after which we'll be happy to take questions. The slide deck we will be referencing is available on our website at calibremining.com under the Events section. You can also click on the webcast to join the live presentation. With that, I'll turn the call over to Darren.
Darren Hall: Thanks, Ryan. Moving to Slide 3. Good morning, and thank you for taking the time to join us today. Firstly, I'd like to thank all Calibre employees and business partners for their continued efforts and focus during what has been a very busy quarter. First of all, I want to acknowledge and I'm proud to make particular mention of the Valentine team for their outstanding safety performance, which was recognized on Monday, when the Canadian Institute of Mining, Metallurgy and Petroleum awarded a team with the prestigious John T. Ryan National Safety Award, a significant achievement and well done to the entire team. Moving to Q1. Consistent with H1 expectations, the company delivered 61,700 ounces of gold in the first quarter. With higher tonnes mined and processed, costs were as anticipated higher than full year expectations. Additionally, with the team in Nicaragua making good progress in the open pits. We are 20% ahead on total material movement which is a little double dazed as it results in higher Q1 spend with derisked production in H2. As we have consistently foreshadowed, gold production is H2 weighted and I'm confident in reaffirming our full year guidance. Turning to Slide 4. Our vision at Calibre has always been to establish a quality mid-tier gold producer by generating strong operating cash flow to fund organic growth while seeking accretive opportunities to diversify and grow. We have consistently delivered into this vision never more so than now with the acquisition of the Valentine Gold Mine in Newfoundland and Labrador. With first gold scheduled in Q2 2025, Valentine will establish Calibre as a quality mid-tier gold producer in the Americas, providing a compelling re-rate opportunity for all shareholders. I'm pleased to report the construction of our fully funded Valentine Gold Mine is 64% complete, and we have progressed detailed engineering to 98%. Additionally, the team has completed the tailings management facility started there, received Engineer of Record sign up commenced line of placement, which is a significant milestone in the project development; delivered critical path items including mills and motors to Newfoundland. We recently enclosed the mill building, we've connected site to permanent hydroelectric power. We've awarded all major outstanding construction contracts, employed experienced and highly motivated operations leadership team, and awarded a contract for an advanced pre-commissioning and commissioning activities. These project optimization and derisking efforts, combined with the accelerating operational and a portion of Phase 2 capital expansion results in initial capital costs of $653 million, $145 million increased of Marathon Gold's Q3 2023 update. With $279 million in additional project capital remaining to be spent and $400 million in cash from restricted cash, the bill is fully funded. Moving to Slide 5. The $145 million is consistent with our pre-acquisition due diligence and incorporate underestimated costs, inflationary impacts and capital advised by Calibre to derisk delivery and to support future operations. The increase versus Marathon's Q3 2023 estimate primarily consists of three components: schedule and cost estimation of approximately $70 million, which relates to improved quantity, cost and prime estimates with engineering now at 98%, progressed from 60%, which was the basis of the Q3 2023 estimate. Secondly, $40 million attributable to Calibre's project optimization and derisking efforts which focus on ensuring that the facility, as designed, delivers its full potential as we transition from construction to operations. This investment includes pre-commissioning and commissioning, planning and activities, mill and site modifications, access road upgrades and importantly, advancing deployment of the operations team. Finally, Calibre is advancing operational, Phase 2 capital expansion of $35 million, which is more opportunistic in nature and includes investment in infrastructure that will positively impact operations. This includes commencing construction of permanent mobile equipment maintenance facilities, process plant effluent treatment plant and accommodation upgrades. A more strategic component of this investment advances a portion of the Phase 2 expansion capital. In the feasibility study Phase 2 is the planned plant expansion in years 3 and 4, which has increased throughput to 4 million tonnes per year. We are early in the analysis and given the current SAG or circuit side, we believe there may be opportunity to increase throughput in advance of a plant expansion. A key component to enable any increased throughput would be to ensure that capacity in the CIL circuit and therefore, we have included additional tankage as anticipated in the Phase 2 design. We've commenced a scoping study to review process plant expansion options focused on assessing combination circuit alternatives. It's early in the analysis but I'm encouraged with the recombination of secondary fraction and grinding options, which may present even higher return options than the feasibility study envisage Phase 2, which is a good segue into exploration as having an appreciation of the potential scope of the district will influence scale when assessing processing expansion opportunities. The Valentine Gold Mine and surrounding property offers a robust resource base and discovery opportunities from an extremely prospective array of exploration targets with similar geology to the prolific Val-d'Or and Timmins camps in the Abitibi gold belt. I'll now pass it to Tom to provide additional color on Valentine's exciting exploration.
Tom Gallo: Thanks, Darren. Turning to Slide 6. The 250-kilometer square Valentine land package offers us a considerable resource base from which to grow. The discovery potential in our view is high with an underexplored orogenic setting. The 2024 exploration program will include resource expansion and discovery drilling backed by a robust geoscience initiative similar to what we've employed in our other jurisdictions and we'll focus on high-definition property-wide geophysics and LiDAR survey, enhanced prospecting and a comprehensive TIL sampling program. Several targets, which have never been drilled but are a high priority for Calibre include Eastern Arm, Northwest Contact, Western Peninsula and Marathon Northeast. In addition to the regional potential, it is important to highlight the recently completed ore controlled drilling at Leprechaun, which bolsters our confidence in model performance. The results substantiate the mineral reserve estimate in the first five benches the drilling indicating an increase in ore tonnes of 15% and overall gold ounces of 12%. Additionally, high-grade gold mineralization was discovered on the southwest edge of the pit, highlighting strong resource expansion potential given the limited drilling along the Valentine Lake Shear Zone toward the Frank deposit. Phase 1 diamond drilling has now been completed. We are scheduled to follow up along the Frank-Leprechaun corridor with a more detailed program in the fall. Overall, early-staged, drill-ready targets backed by surface anomalies, which have never been drilled, combined with near mine expansion potential, demonstrate the robust nature of this mineral system. The Valentine Lake Shear Zone and Northwest Contact Shear Zone combined for up to 64 kilometers of high potential opportunity with over 5 million ounces of gold hosted. As we quickly increased our knowledge base throughout the field season and with incoming drillable assays, I would anticipate this could lead to a much larger drill program in the future. With that, I'll turn it back over to Darren.
Darren Hall: Thanks, Tom. Moving to Slide 7. With construction of 64% and detailed engineering is 98%, Calibre is well positioned to responsibly deliver the fully funded Valentine Gold Mine. With first gold scheduled in Q3 2025, the delivery of Valentine presents a paradigm shift to Calibre as we transition to a quality mid-tier old producer, which will unlock significant value for all stakeholders. With that, we're happy to take questions, and I'll pass it back to the operator.
Operator: Thank you very much. We will now begin the question-and-answer session. [Operator Instructions] Today's first question comes from Ingrid Rico with Stifel. Please go ahead.
Ingrid Rico: Hi. Good morning, Dan and team. Thank you for taking my questions. I'll probably start with just sort of on the capital. You gave us the update on a lot of the major contracts have been awarded. So Darren, what's sort of outstanding on the critical path right now. What should we be looking for over the next six months?
Darren Hall: Yeah. Hi, Ingrid. Good morning. In the personal, thanks for initiating coverage there. In Q1, it is appreciate the knowledge. Thanks. Well done. In terms of outstanding major items, to note, we've kind of mentioned where we're well progressed on the engineering where three-quarters built. The mills, modes are on site. In terms of major deliverables are probably in relation to the conveyors, which come later in the summer. And but again, there's plenty of time for those deliveries. So I don't see them as really critical path. The major contracts in terms of the S&P's structural mechanical and piping was main issue. A list of instrumentation is, we’ve got a letter of intent. And we're in the final stages of issuing that contract, bringing together those groups of people and scheduling that out through the summer to bolt things together is probably critical path. So it's not so much delivery. It's more about assembling the mechanics, if you will. And that's where the theme of focus on now is, is that it's now into truly the execution and all bolting things together. The major civil works are done with Middle East, the risk from a technical perspective that mill building is now a close. So now it's really that fine detail about bolting all those things together and the coordination of a significant number of people who come together during the construction season here in the summer. So I think it's more around execution of those words, it is critical parts and service delivery of bits and bolts.
Ingrid Rico: Excellent. And on the operation readiness, you've talked about having now the leadership team, but how is the sort of recruitment process going, what are sort of the targets over the next few months to get fully staffed for, for operations?
Darren Hall: Yes. Thanks. Thanks, Ingrid. And I guess is there enough, I thought cycle back in time to when we close the trends, the transaction, probably one of the concerns I had was assembling the leadership team and we've had excellent take-up over the last three months. And again, we had a good core of people to bolt on with, Daniel and Mike at site. But now we think about the 10 most senior people in the operation of all of those positions have currently been employed. So if we think of mine managers, mill managers, process managers, construction managers into the operations by business manager health and safety, all of those positions are now filled, and we've done that over the last couple of months, which is unnervingly pleasing given the apparent shortage of labor in Canada. So I think that attracting people into the province has been easier than anticipated. And all of the top 10 or nine of the top 10 are actually -- have actually or are relocating to Labrador in the winter and Central Newfoundland as well. So they'll be living local and commuting in. So that's a great thing. We know we've got a significant resource base in here in Newfoundland to hire from terms of operators and mill rights and mechanics and those sort of things. So hiring into that space. There is definitely a lot of talent there, and there's obviously a significant number of people who work turnarounds who are wanting to come back. So I think the challenge we'll probably have on a labor perspective is some disappointment that we won't be able to provide everyone with the job they wanted. So I'm feeling actually very confident in that space. I'll be back on site here in another week for a couple of weeks as we kind of assembled the team and do a little bit of Calibre 101, bring them all together and make sure they've got what they need to be able to deliver into the expectations here in Q1, but we've seen a great pickup with the projects team. And I think importantly, having a group like RCC come in as well on the pre-commissioning and commission to ensure that those two groups come together is a critical component as well. So a long-winded answer to a pretty short question there, Ingrid, but I'm very pleased with the progress we've made on hiring. I'm very pleased with the quality of people we've got. And they're also very motivated in the fact that the relocation to Newfoundland and taking up the opportunity to live in a great place. So yeah, feeling more and more comfortable with every day that goes forward.
Ingrid Rico: That's great to hear and thank you for all that sort of update. If I may ask just one last question, On mining. I wanted to ask on, Berry, I understand that this federal permits still outstanding. Can you sort of tell us a little bit of what's the latest on that and when are you expecting to receive it? And I guess based on your sort of re-baseline schedule, when do you need to start mining Berry?
Darren Hall: Okay. Yeah. No, good question. And Berry, the original intent, I think, was that Berry was going to start running at either late this year or very early in 2025. We're confident in the permitting process. It's been through the provincial EA review, and they've got an early release. From memory, I think that was in October of 2023, then came across to the federal piece. The federal group, which, again, I'll say if I can get the acronym correct, I think it's IAAC, which is Impact Assessment Agency of Canada. They completed their public comment period here in end of March, which is a very good sign as well because it kind of foreshadows their intention to approve. So no, I think it's all kind of going as planned. I mean we haven't seen any significant public comment from our external parties as part of the federal review. I think the federal government are working through some issues with respect to process because I believe there was a comment made by the Supreme Court that they thought the process was overreaching, right, which is great. I mean, I'd rather be overreached by a regulatory and make sure that we're doing the right things to ensure that our stakeholders are protected, but I don't anticipate that to materially slow down the approval process. So -- and this relates to all projects in Canada, right? It's not just us. So no, I'm still confident in. But now to say, well, there's always risk and we tend to be a little conservative in approach, which is probably not a bad way to be. So when we did the re-baselining and as we've continued discussions with our senior debt folks as well, is that I said, look, let's just take it out of the discussion context, and we'll push Berry out from a commencement until early Q3 of 2025. And then there's an opportunity to drag it forward if we see the opportunity and produce a little bit more metal really, which is never a bad thing. So yes, I'm not concerned about it, but it absolutely is the focus to ensure that we deliver into expectations. But we've derisked the schedule by taking it out of contention. So that way, it's a positive when it comes back in as opposed to pushing it out.
Ingrid Rico: Great. Thank you, Darren.
Darren Hall: Sorry, just -- actually, just as a layer on that, I think out loud as you being kind of a more technical person as well, Ingrid, is that we think about the 2025 production schedule. And Berry was one component of the three and basically pushing the production. Producing Berry out derisk that production profile but with Leprechaun and Marathon producing as planned. that's significantly -- I won't say derisk, but delivers into the expectations. And from memory, and again, it's been a while since I've -- little shakes out of big shakes in mine site, but I think we're looking at probably 2 million to 2.5 million tonnes of inventory in stockpile at the end of 2025. So given those sorts of things you're likely to see on startup, we've got more than adequate capacity to offset any of those bits and bops that come up.
Ingrid Rico: I appreciate that. Thank you, Ryan, for passing along that question. I was looking for some of that color last night. Thank you.
Darren Hall: I appreciate that. Thanks, Ingrid. Appreciate your support.
Operator: Thank you. The next question is from Don DeMarco with National Bank Financial. Please go ahead.
Don DeMarco: Thank you, operator, and good morning, Darren and team. Congratulations on all the derisking. Was this Valentine update? So first question, for increasing the throughput to 3 million tonnes per year and I get it that is probably still has to be subject to its own de-risking improving. But how would you expect that to change the production profile versus the feasibility study in the first few years?
Darren Hall: Yeah. Don, 3 million tonnes, that sounds like a good number. Again, that's part of what we're working through right now, is that the design work that was done initially with SAG ball is very, very solid. It's good quality product, good work. As we go through some of the -- looking at the analysis for that grinding and crushing optimization in 2025. I think there will be potential to exceed what would be that 2.5 million tonnes. When that happens, I can't necessarily say categorically right now, but I think there is good potential. And that's part of the reason why we advanced the Phase 2 capital into this construction build. It's not required to but adding that 30% increase in tankage positions us well to be able to realize any potential that comes from increased throughput. So yes, no, we'll work it through as we get closer. And I think that an important part of what we're looking at now is that first set of eyes, if you will, looking at the Phase 2 expansion and what that really looks like, I think that as envisaged, it's solid and it's good. But I think that given the configuration of the crushing and the grinding circuit, there's going to be options to look at maybe it's a secondary stage crusher and tertiary stage milling or maybe it's a pedal crusher after the SAG and increase combination capacity and push those tonnes as well earlier. So we'll work it through and as we have a high degree of confidence, we start to talk more openly about it. But albeit right now, I'm pretty confident in what we see and anything we do will obviously improve the positioning of Valentine as we transition into production here in 2025.
Don DeMarco: Okay. Well, good to see that upside there, and we'll look for more color as you get closer to that. So you got the contract with RCC for commissioning -- pre-commissioning and commissioning. Can you tell us a little bit about this? I mean maybe the scope of work or your experience working with these guys or some of the other -- the work you've done in the past and so on?
Darren Hall: Yes, absolutely. It's not typical of companies outside of projects for this size to have a group like RCC involved. They've got quality output. We've got Tim McKay and he's assembling a team or assembled a team that's able to support us. And the real focus here is that to bridge what is the project team who are focused on scope, schedule and budget on getting to the delivery room. And then we've got an operations team who want to pick the child up once is delivered and raise it into a responsible adult. Yes, this group of people are really ensuring that transition and handover happens well. And the operators are great at operating client, but putting in place the processes by which you're going to operate to ensure that and realize the full potential of the asset is not always a strong point, particularly as they're hiring teams of people. So really, as I see, that's what that -- the focus of this group is, is to help us. And it's a material cost. I mean we're talking the pre-commissioning, commissioning activities are in the order of Canadian dollars, probably around $9 million to $10 million. I mean it's a significant commitment we're making, but it significantly derisks the medium, longer term. The last exposure I had with this group of people was actually at Boddington. They did the pre-commissioning commission works at Boddington in Australia when we delivered that asset. So it's a very experienced group of people. This is what they do for a living. They're not engineers. They don't do -- they're not a pain and do process optimization and those sort of things. It's not that sort of group. All they do is this is their bread and butter. So a good group of people, great to have them on board. And we've got a great project team to deliver the asset. We've got a great operations team to be able to run the asset. And I think that adding this third link to the stool makes for a very stable chair.
Don DeMarco: Okay. It's good to see there's that derisking there then. And maybe just a final question, does this discovery along the Southwest edge of the Leprechaun pit, we've seen some press release, some intercepts are looking encouraging. But does this have potential could be mined early in the mine life if it continues to be proven out and is converted to reserves and so on?
Darren Hall: Well, I think there's a couple of parts to this, and I'll maybe throw it over to Tom, if there's anything I miss. But some of what was identified in that Valentine's Day release is that will be mined as a consequence of because it's inside of the pit. It wasn't actually identified as -- well, two parts, some of was identified as inferred, which we've improved the confidence to measure an indicated category. Some of it was never identified, so it's considered as waste. So that waste now becomes ore. So we don't actually process measured indicated in 2P, we process whatever ore presents out of the ground. So that means that will end up as available grist for the mill as it were. But as it kind of bleeds off there to the Southwest towards Frank, I think that Tom and the exploration guys are very encouraged by what they see in terms of the ability to expand into. Tom, is there anything you'd layer in this? Because actually, Tom, I think is in the room here. He's actually in Nicaragua this week
Tom Gallo: Yeah. No, I think you covered it. I mean, I think it is important to understand that we will have ounces sort of, by default, come into the mine plan because they were not captured previously. And so they'll do things like lower the strip ratio in place or just add bonus ounces, and that's part of why we saw that increase in tonnage and subsequently overall ounces in that grade control because the tonnage actually comes from things that weren't categorized. To the southwest, once you get outside the bounds of the pit, there's still considerable work that needs to be done from a drilling perspective. Definitely encouraged with what we've seen visually, don't have all the assays in to speak about yet from our first phase of diamond drilling that was completed in Q1. But of course, this is a very visual ore body, so we can see where the mineralization should be. We do have indications on surface as well of that same mineralization continuing fairly regularly down to Frank where we did that drilling. So again, there's some follow-up work to do there, but it's very consistent on from what has been what -- we've known and to be the, let's call it, Marathon-style QTP, quartz-thormaline-pyrite in the Trondhjemite mineralization, right, and I followed the story as an analyst back since 2017. So it's very consistent from what we've been familiar with.
Don DeMarco: Okay. Well, thanks. Thanks for that, Tom and Darren, that's all for me. Good luck with the rest of the build.
Darren Hall: Okay. Thanks and appreciate your support and coverage.
Operator: Thank you very much. This concludes our question-and-answer session. I would now like to turn the call back over to President and CEO, Darren Hall for closing remarks.
Darren Hall: Thanks, MJ. I would like to thank all of our shareholders for their continued support. And in particular, your participation and questions this morning, it is appreciated. Thank you for taking the time. I know it's a busy time of the year for everyone. As always, Ryan, I and the leadership team are available if you have any further questions. Take care. Have a safe and enjoyable day. And back to you, MJ.
Operator: Thank you very much. The conference has now concluded. Thank you for attending today's presentation. You may now disconnect, and have a nice day.
This article was generated with the support of AI and reviewed by an editor. For more information see our T&C.