UPDATE 1-EQM stops some work on WV-VA Mountain Valley natgas pipe

Published 2019-08-16, 09:49 p/m
UPDATE 1-EQM stops some work on WV-VA Mountain Valley natgas pipe
ED
-
NG
-
NEE
-
RGCO
-
ALA
-

(Adds EQM comment)

Aug 16 (Reuters) - EQM Midstream Partners LP EQM.N has told U.S. federal regulators the company would stop some work on its long-delayed Mountain Valley natural gas pipeline from West Virginia to Virginia as the U.S. Fish and Wildlife Service reviews a couple of permits.

In a letter to the U.S. Federal Energy Regulatory Commission (FERC) on Thursday, EQM said it was voluntarily suspending new work on Mountain Valley in areas where such activities present a potential risk to endangered species or destruction of critical habitat areas.

EQM said on Friday it plans to continue construction in other areas along the route and is still targeting a mid-2020 full in-service date for $4.8-$5 billion pipeline.

EQM's decision to suspend work was in response to a lawsuit filed by the Sierra Club earlier this week in the U.S. Court of Appeals for the Fourth Circuit, according to analysts at Height Capital Markets in Washington, which expects the project will not enter service until in the third or fourth quarter of 2020.

In that case, the Sierra Club asked the court to vacate Mountain Valley's biological opinion and incidental take statement, which allow construction of the pipe in areas inhabited by threatened or endangered species.

The analysts said they do not expect the Fish and Wildlife Service or EQM will pursue litigation since the Fourth Circuit would likely side with the Sierra Club as the court did in a case against another long-delayed project - Dominion Energy Inc's D.N Atlantic Coast pipe from West Virginia to North Carolina. EQM decided to voluntarily suspend work, the analysts said, noting the company had already completed building in those areas or was barred from working in them until it gets a new permit from the U.S. Army Corps of Engineers that would allow the pipe to cross streams and other water bodies. Capital expects the Army Corps will reissue the permit in coming months.

When EQM started construction in February 2018, it estimated Mountain Valley would cost about $3.5 billion and be completed by the end of 2018. 303-mile (488-km) pipeline is designed to deliver 2 billion cubic feet per day (bcfd) of gas. One billion cubic feet is enough gas to supply about 5 million U.S. homes for a day.

Mountain Valley is owned by units of EQM, NextEra Energy Inc (NYSE:NEE) NEE.N , Consolidated Edison Inc (NYSE:ED) ED.N , AltaGas Ltd ALA.TO and RGC Resources Inc RGCO.O .

Global Intelligent Motor Control Center Market to Reach $3.74 Billion by 2026 - ResearchAndMarkets.com

U.S. asks Supreme Court for more time on Atlantic Coast natgas pipe appeal

FACTBOX-U.S. new natural gas pipeline projects

UPDATE 3-EQM says 'unlikely' to complete Mountain Valley natgas pipe in 2019

UPDATE 2-U.S. court vacates Dominion Atlantic Coast natgas pipe permit

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.