Nov 30 (Reuters) - Kinross Gold Corp K.TO :
* Kinross' paracatu mine returns to full production
* Says temporary curtailment of plant 1 and plant 2 is expected to impact
production by a minimum of 16,000 gold ounces in Q4
* Says company expects to be within its production guidance for the year of 2.5
- 2.6 million au eq. oz
* Temporary curtailment of plant 1 and plant 2 is expected to impact production
by maximum of 34,000 gold ounces in Q4 2015
* Source text for Eikon ID:nMKWgXP68a
* Further company coverage K.TO