Oct 26 (Reuters) - Hudbay Minerals Inc HBM.TO :
* HUDBAY MINERALS - GIVES UPDATE ON INSPECTION COMPLETED TO DATE AT 777 MINE IN FLIN FLON, MANITOBA, FOLLOWING SKIP HOIST INCIDENT ANNOUNCED ON OCT. 11
* HUDBAY MINERALS - UNDERGROUND MINING ACTIVITY HAS RESUMED AT 777 WITH LIMITED PRODUCTION FROM MINE'S RAMP ACCESS
* HUDBAY MINERALS - IF CONFIRMED THERE IS NO DAMAGE BEYOND WHAT HAS BEEN IDENTIFIED TO DATE, EXPECTED 777 SHAFT COULD RESUME FULL PRODUCTION IN DEC.
* HUDBAY MINERALS INC - REPAIR COST FOR DAMAGE NOT EXPECTED TO EXCEED $5.0 MILLION
* HUDBAY MINERALS INC - Q4 PRODUCTION AND SALES VOLUMES WILL BE IMPACTED
* HUDBAY MINERALS - IMPLEMENTING PRODUCTION MITIGATION PLANS, EXPECTS MANITOBA BUSINESS UNIT TO ACHIEVE FY PRODUCTION, UNIT COST GUIDANCE FOR 2020