Earnings call: Aecon reports mixed Q2 2024 results amid project challenges

EditorNatashya Angelica
Published 2024-07-26, 03:04 p/m
© Reuters.
ARE
-

In the second quarter of 2024, Aecon Group Inc. (ARE) reported a decline in both revenue and adjusted EBITDA compared to the same period in the previous year. This was largely attributed to non-recurring charges related to the Coastal GasLink Pipeline project and other legacy projects. However, when excluding these one-time impacts, revenue remained relatively stable year-over-year.

Aecon's reported backlog stood at $6.2 billion, and the company discussed ongoing efforts to diversify its portfolio and improve profitability. The acquisition of Xtreme Powerline Construction is expected to contribute positively to Aecon's focus on the energy transition.

Key Takeaways

  • Aecon's Q2 2024 revenue and adjusted EBITDA decreased due to non-recurring charges.
  • Excluding these charges, revenue was comparable to the previous year.
  • The company's reported backlog was substantial at $6.2 billion.
  • Aecon is focusing on completing legacy projects and pursuing fair settlements.
  • Growth opportunities in decarbonization, energy transition, and international markets are being actively pursued.
  • Aecon aims for improved profitability and margin predictability, with a reduction in fixed price work to balance risk.
  • Development phase projects are expected to transition to construction in 2025, potentially doubling the backlog.
  • Aecon acquired Xtreme Powerline Construction to strengthen its position in the energy transition market.

Company Outlook

  • Aecon is committed to building a resilient company through a diversified work portfolio.
  • The company expects further revenue growth in the coming years.
  • Aecon is focused on achieving improved profitability and margin predictability.
  • The company is looking to add to its concessions business within the next 12 to 24 months.

Bearish Highlights

  • Aecon identified additional financial risks up to $125 million, mainly from potential cost creep and schedule slippage.
  • The company's earnings profile may be impacted by the stability of airport and other concession contracts over the next 18 to 24 months.

Bullish Highlights

  • Aecon sees growth opportunities in decarbonization and the energy transition.
  • The company is involved in refurbishment programs and the development of small modular reactors (SMRs), with potential for growth in Canada and internationally.
  • Aecon's bid pipeline remains strong, indicating sustained demand for its services in Canada.

Misses

  • The company's revenue and adjusted EBITDA for Q2 2024 fell year-over-year due to specific non-recurring charges.
  • Aecon's legacy projects have experienced delays, impacting overall performance.

Q&A Highlights

  • Aecon provided a current estimate of $110 million for the cost to complete legacy projects but noted a potential risk of $125 million.
  • The company will have better information on the financial risks by the end of 2024 or early 2025.
  • Aecon is optimistic about the integration of Xtreme Powerline and its contribution to the company's growth.

Acquisition of Xtreme Powerline

  • Xtreme Powerline, with over 300 employees in Michigan, is expected to be integrated within Aecon Utilities Group.
  • The acquisition aligns with Aecon's strategy and is expected to enhance its position in the energy sector.
  • Xtreme Powerline's strong relationship with DTE and its capabilities in emergency response projects are seen as valuable assets to Aecon.

In conclusion, Aecon Group Inc. faces challenges with its legacy projects but remains committed to its strategic objectives. The company is working towards enhancing its project selection process and capitalizing on opportunities in emerging sectors such as decarbonization and energy transition. With the recent acquisition of Xtreme Powerline and a strong project backlog, Aecon is positioning itself for future growth and stability.

Full transcript - Aecon (AEGXF) Q2 2024:

Operator: Good day, and thank you for standing by. Welcome to the Q2 2024 Aecon Group Inc. Earnings Call. [Operator Instructions] Please be advised today's conference is being recorded. I would now like to hand the conference over to your speaker today, Adam Borgatti. Please go ahead.

Adam Borgatti: Thank you, Kevin. Good morning everyone and thanks for participating in our second quarter results conference call. This is Adam Borgatti speaking, Senior Vice President of Corporate Development and Investor Relations. Joining me are Jean-Louis Servranckx, President and CEO; Jerome Julier, Executive Vice President and CFO; and Alistair MacCallum, Senior Vice President Finance. Our earnings announcement was released yesterday evening and we posted a slide presentation on the Investing section of our website which we'll refer to during the call. Following our comments, we'll be glad to take questions from analysts and we ask that analysts keep to one question and a follow-up before getting back into the queue. As noted on Slide 2 of the presentation, listeners are reminded that the information we're sharing with you today includes forward-looking statements. These statements are based on assumptions that are subject to significant risks and uncertainties. Although Aecon believes the expectations reflected in these statements are reasonable, we can give no assurance that these expectations will prove to be correct. And with that, I'll hand the call over to Jerome.

Jerome Julier: Thanks, Adam and good morning everyone. I'll touch briefly on Aecon's consolidated results review, results by segment address Aecon's financial position and then discuss our legacy projects before turning the call over to Jean-Louis. You will see that there have been quite a few developments. So we've added additional information to help clarify the underlying results. Detailed [Technical Difficulty] tables are available on Slide 16 and 17. Turning to Slide 3. On a reported basis, revenue for the three months ended June 2024 of $854 million was $313 million or 27% lower compared to the same period in 2023. Adjusted EBITDA of negative $153 million compared to $17 million last year and operating loss of $166 million in the quarter compared to an operating profit of $56 million last year. Adjusted EBITDA and operating profit in the second quarter were negatively impacted by the previously disclosed $127 million non-recurring charge related to the achievement of a global settlement for the Coastal GasLink Pipeline project and the additional aggregate charge of $110 million related to the three remaining legacy projects. Excluding the impacts from the legacy projects and the divestitures, which we will describe as as-adjusted, revenue for the three months ended June 30, 2024 of $975 million compared to $978 million in the same period in 2023. Adjusted EBITDA was $78 million compared to $93 million last year and operating profit was $46 million compared to $64 million last year. Diluted loss per share in the quarter of $1.99 compared to diluted earnings per share of $0.38 in the same period last year. Our reported backlog of $6.2 billion at the end of the quarter compared to backlog of $6.2 billion at the end of December 31, 2023 and $6.9 billion at the end of the second quarter of 2023. New contract awards of $766 million were booked in the quarter compared to $2 billion in the prior period. Now, looking at results by segment. Turning to Slide 4. Construction revenue of $851 million in the second quarter was $288 million or 25% lower than the same period last year. Revenue was lower in industrial operations, primarily due to decreased activity on mainline pipeline work, following the achievement of substantial completion on the Coastal Gaslink Pipeline project in the third quarter of 2023, which offset a higher volume of wastewater treatment facilities work. Revenue was lower in the urban transportation solutions from a lower volume of LRT work in Ontario and [Technical Difficulty] sale of Aecon Transportation East in the second quarter of 2023 and from a lower volume of major project work following completion of a large hydroelectric project in 2023. Partially offsetting these decreases was higher revenue in nuclear operations driven by an increased volume of refurbishment work and in utility operations from a higher volume of electrical transmission and battery energy storage system work, partially offset by lower volumes in telecommunications and gas distribution. On an as-adjusted basis, construction revenue was $973 million flat to last year. New contract awards of $763 million in the second quarter of 2024 compared to $2 billion in the same period last year. New awards in the second quarter of 2023 were bolstered by significant adjustments in nuclear operations. Backlog at the end of the second quarter of $6.1 billion compared to $6.8 billion at the end of the second quarter of 2023 which included roughly $200 million of pipeline-related backlog at the time. Turning now to Slide 5. Adjusted EBITDA of negative $173 million compared to negative $4 million last year. As previously noted, the decrease was largely driven by negative gross profit on the four legacy projects of $237 million in the second quarter of 2024 compared to negative gross profit of $81 million on these projects in the same period last year. Adjusted EBITDA in the second quarter on an as-adjusted basis was $64 million compared to $78 million last year with the variance being driven by lower gross profit in urban transportation solutions from rail electrification work, increases in corporate costs and partially offset by improving performance in our nuclear operations. Turning now to slide 6. Revenue for the second quarter was $2 million compared to $27 million in the same period last year. The decrease in revenue was largely driven by the sale of a 49.9% interest in Skyport the Bermuda Airport concessionaire and commencement of the equity method of accounting for Aecon's retained 50.1% interest in Skyport. Adjusted EBITDA in the Concession segment of $30 million compared to $28 million last year. Operating profit related to the Skyport asset was higher in the second quarter driven by one-time recoveries of $5.9 million in 2024 and an incremental gain on sale of $5.9 million reported in 2024 related to additional proceeds earned in the 2023 partial sale of Skyport. On an as-adjusted basis operating profit in the Concession segment in the second quarter was $5 million compared to $9 million last year reflecting lower development fees and higher costs associated with pursuits on energy transition endeavors. On slide 7 we've brought together the information to exclude the impact of the legacy projects and divestitures to provide insight into the underlying performance of the business. Adjusted revenue for the trailing 12-month period ended June 30, 2024 was $3.8 billion compared to $3.7 billion for the same period last year. Adjusted EBITDA including the previously noted adjustments was $344 million in the trailing 12-month period compared to $343 million in the same period last year. For the Construction segment on an as-adjusted basis the EBITDA was $305 million for the trailing 12-month period representing an 8% margin. Turning to slide 8. At the end of the second quarter, Aecon held cash and cash equivalents of $131 million excluding cash and joint operations. In addition, at June 30, 2024, Aecon had committed revolving credit facilities of $850 million of which $98 million was drawn and $4 million was utilized for letters of credit. Netting the cash position against our drawn revolver results in a net cash position of $33 million at the end of the quarter prior to the inclusion of other debt items noted below. Aecon has no debt or working capital credit maturities until 2027 except equipment loans and leases in the normal course. In addition, Aecon's Board of Directors has authorized a normal course issuer bid or NCIB to purchase for cancellation up to 5% of the issue now to any common shares or approximately 3.1 million common shares of Aecon subject to the approval of the TSX. Aecon intends to file a notice of intention with the TSX in this regard and if accepted NCIB shortly thereafter. Turning to slide 9. I'll now provide an update on our legacy projects. On June 28, SA Energy Group in which Aecon is a 50% general partner and Coastal GasLink Pipeline LP reached an amicable and mutually agreeable global settlement to resolve their dispute fully and finally over the construction of Sections 3 and 4 of the Coastal GasLink Pipeline Project in BC. The settlement agreement is not an admission of liability by either party and the parties have mutually released their respective claims in the arbitration thereby avoiding the expense, burden and uncertainty associated with the arbitration. The terms of the settlement agreement are expected to result in no cash impacts to Aecon. As noted previously from an accounting perspective Aecon recognized a non-recurring charge of $127 million in the second quarter of 2024 related to the settlements. The Coastal GasLink settlement allows Aecon to close the chapter of one of the most technically and financially challenging projects in its history and we want to thank our team for delivering the project safely and with incredible resiliency through to completion. Progress continues on the two LRT projects in Ontario including signaling and train control systems testing and advances in driver training for the operator. Physical work is nearly complete with the most station and structure of occupancy permits received. Full vehicle testing is also ongoing across the projects. However, forecasted substantial completion dates have been delayed due to setbacks and meeting necessary testing, commissioning and additional training and coordination requirements with the operator. As seen on the cover of the presentation the deck on the Gordie Howe International Bridge between Windsor and Detroit is now connected. This is a significant accomplishment creating the longest cable stayed bridge span in North America. Work is progressing on the main bridge and on the Michigan Interchange as well as on the two international port of entry facilities and their core systems. However, additional costs have been incurred related to the bridge and Michigan Interchange structures and finishes as well as other areas such as the finishes in the mechanical and electrical systems of the port of entry facilities. As a result of these impacts, Aecon recognized an aggregate charge of $110 million in the quarter from the remaining three legacy projects reflecting our current estimates on the cost of completion for these remaining projects. Aecon believes our estimates to be accurate as of today, and the majority of the risks for the remaining three legacy projects are largely behind us. However, additional risks exist if assumptions, estimates and circumstances change until the projects are substantially complete. To that end, we are providing a risk analysis that reflects negative changes to our assumptions, which could potentially impact our cost to complete on these projects. Based on the information currently available, Aecon believes the potential for future additional financial risks to Aecon, if any, through to completion of the remaining three legacy projects should not exceed $125 million through the end of 2025. We remain focused on driving the remaining legacy projects to completion, while pursuing fair and reasonable settlement agreements with their respective clients in each case. Of the remaining three projects, one is currently expected to be substantially complete by the end of 2024, another in early 2025, and the final project by the end of the third quarter of 2025. At June 30, 2024, the remaining backlog to be worked off on the legacy projects was $269 million compared to backlog of $420 million at December 31, 2023 and $699 million at June 30, 2023. At this point, I'll turn the call over to Jean-Louis to address our business performance and outlook.

Jean-Louis Servranckx: Thank you, Jerome. Turning to slide 10. Aecon's goal is to build a resilient company through a balanced and diversified work portfolio, while enhancing critical execution capabilities and project selection to play to our strengths. We continue to leverage our self-perform capabilities and One Aecon approach to maximize value for clients through improved cost certainty and schedule, while offering a broad range of services from development, engineering, investment and construction to longer-term operations and maintenance to cover the full infrastructure value chain. While we pursue and deliver the majority of our work in established markets, we are embracing new opportunities to grow in areas linked to decarbonization and the energy transition and in US and international markets. Our acquisition of Xtreme Powerline, which we will discuss further aligns with this approach. These opportunities are intended over the long term to diversify Aecon's geographic presence, provide further growth opportunities and deliver more consistent earnings through economic cycles. Turning to slide 11. Demand for Aecon services across Canada continues to be strong, with backlog of $6.2 billion at June 30, 2024. Recurring revenue programs continuing to see robust demand and a strong bid pipeline. Aecon believes it is positioned to achieve further revenue growth over the next few years and is focused on achieving improved profitability and margin predictability. We are pursuing a balanced portfolio of work delivered through both fixed and non-fixed price contracting models, with the goal of reducing fixed price work to balance risk with acceptable returns. Trailing 12-months recurring revenue of $1.1 billion was comparable to the prior period and up 38% versus two years ago. Contribution from the GO Expansion On-Corridor Works and Scarborough Subway Extension projects during the respective development phases increased in the quarter, which offset a lower volume of gas distribution and telecommunications works in utilities operations and impact from the sale of ATE last year. Adjusting for the impacts of the sale of ATE and the 49.9% interest in Skyport, recurring revenue increased 9% on a like-for-like basis over the trailing period last year. Turning now to slide 12, development phase work is underway in five consortiums in which Aecon is a participant to deliver the GO Expansion On-Corridor Works project, the Scarborough Subway Extension project, the Darlington New Nuclear Project, the Contrecoeur Terminal Expansion project, and the US Virgin Islands Airport Redevelopment Project. These projects are being delivered using collaborative progressive design build models, and each project is expected to move into the construction phase in 2025. The GO Expansion project also includes an operations and maintenance component over a 23-year term, commencing January 1, 2025. As a reminder, none of the anticipated work from these five progressive design build projects is yet reflected in backlog, but could in aggregate increase our backlog in 2025 to approximately double the level of our current backlog. Turning to slide 13. With strong demand growing recurring revenue programs and diverse backlog in hand, Aecon is focused on achieving solid execution on its projects and selectively adding to backlog through a disciplined bidding approach that supports long-term margin improvement in the Construction segment. In the Concession segment, there are a number of opportunities to add a to the existing portfolio of Canadian and international concessions in the next 12 months to 24 months, including projects with private sector clients that support a collective focus on sustainability and the transition to a net zero economy as well as private sector development expertise and investment to support aging infrastructure, mobility, connectivity and population growth. Revenue in 2024 will be impacted by the three strategic transactions completed in 2023, the substantial completion of several large projects in 2023, the four legacy projects and the five major projects currently in the development phase by consortiums in which Aecon is a participant being delivered using the progressive design build or alliance models, which are expected to move into the construction phase in 2025. The completion and satisfactory resolution of claims on the remaining three legacy projects remains a critical focus while the remainder of the business continues to perform as expected, supported by the strong level of backlog and the strong demand environment for Aecon services, including recurring revenue programs. Finally, turning to slide 14. On July 2, Aecon Utilities Group acquired a majority interest in Xtreme Powerline Construction, an electrical distribution utility contractor, headquartered in Michigan for a base purchase price of approximately $73 million, with the potential for additional contingent proceeds. Xtreme is a full-service powerline constructor with approximately 300 employees, specializing in overhead distribution line repair, maintenance, expansion and emergency restoration services throughout the Eastern United States for over 20 utility clients. The acquisition of Xtreme creates opportunities to harness our collective utility infrastructure expertise and drive continued growth in priority markets. Xtreme's experienced team and strong client relationships are aligned with our business and we, along with our strategic partner Oaktree, are pleased to welcome the Xtreme team to help advance our continued growth across North America with a focus on the energy transition. As a final comment, I would like to thank our team members for their enduring efforts and ongoing focus on safety and consistent execution. I would like to call specific attention to our Kingstown Port team in St. Vincent and the Grenadines, who are leading a fundraising effort to support the recovery from Hurricane Beryl. Thank you. We will now turn the call over to analysts for questions.

Operator: [Operator Instructions] Our first question comes from Jacob Bout with CIBC (TSX:CM). Your line is open.

Jacob Bout: Good morning. My first question is on margins. It seemed a bit soft in the core construction group. Maybe just talk through what happened in the quarter. And I know last quarter, I think on a TTM basis they were around 9.5%. Is that what you would consider normal course on an annualized basis?

Jerome Julier: Hi, Jacob, it's Jerome here. Good question. So from a margin perspective in the quarter on the construction side of the business on as-adjusted basis we delivered 6.6%. We need to remind ourselves versus last year where we delivered 8%. We had some benefits last year with regards to certain projects on the UTS division and just general strong revenue and productivity. Q2 is not like a high-production quarter for us. We generally tend to backend weight the production through the Q3 and Q4 period. So I'd say in the overall quarter nothing exceptional. There's certainly room for ongoing focus and improvement on the margin profile and execution. With regards to the overall business what I just noted again just focusing on the construction side, margin profile on an LTM basis was 8%. We view that as a strong performance reflecting overall consistent execution from the team -- doesn’t really -- given the work programs that we're engaged with one quarter in isolation doesn't really fully tell the story. I think the right way to look at it is over time and I think that the 8% delivery is there room for improvement on that? Potentially for sure. It's a focus for the team. That's still a pretty productive level for a construction business. If we take it at the aggregate consolidated basis 9% margin there is a benefit that we accrue there on the accounting protocols for the concessions business where revenue has effectively been derecognized on the Bermuda asset. And so we're effectively just picking up an EBITDA contribution. And so from that perspective, the 9.5% that was -- last year on an as adjusted basis would be a very strong result. But if you can look on an LTM basis, I think what we produced was a pretty good indicator.

Jacob Bout: Okay. Maybe just a follow-up there. As you move to a more collaborative project model, maybe just talk through some of the embedded margins in those six projects that you've got coming up?

Jean-Louis Servranckx: Yes. I will take this one Jacob. What is important and very interesting for us is a progressive design build model is the predictability of the results and the fact that we co-develop the project with our client during the first 18 months or 24 months. This is extremely important. So we don't give special guidance on special projects. But this model is I would say much more favorable to contractors and evidently will increase our margin predictability. And with this being said to come back to the first part of your question, I mean we are of course tracking the performance of our peers and competitors. I mean, 8% EBITDA on construction activity for the last 12 trailing months if we get out the legacy project impact, it's quite a good performance. So we are rather optimistic for the future of course.

Jacob Bout: Thank you.

Operator: One moment for our next question. Our next question comes from Yuri Lynk with Canaccord Genuity (TSX:CF). Your line is open.

Yuri Lynk: Hi, good morning. Thanks for taking my question.

Jean-Louis Servranckx: Good morning, Yuri.

Yuri Lynk: Good morning. So Q1 was a clean quarter, eight weeks later you take the $110 million charge on the three LSTKs. So something changed quickly there with relation to costs. So how are you now comfortable putting out the $125 million looking out over 18 months? Just what's the difference between that number and the $110 million that was booked and what's changed now to allow you to feel confident putting a number like that out there?

Jerome Julier: Yeah. Hey, Yuri it's Jerome speaking. Thanks for the question. So with regards to our current estimates on the cost of completion which is the $110 million impact that we booked in the quarter that reflects management's best estimate to completion of the projects as of today. So when we talk about these projects and reforecasts in general, there tends to be in some instances step function changes when scheduled slippages are identified and cemented. And that was certainly the case that resulted in the $110 million. I would note that the $110 million is based on the cost to complete estimates that we have. We're confident in those estimates and those reflect the scheduling that we noted which was end of 2024 early 2025 and Q3 2025. So what's candidly changed between now and where this potential risk figure that we've provided if any through the completion, is effectively centered around a couple of things. And what gives us the confidence is number one, the mutually agreeable -- the mutually agreed and kind of final and full settlement of the CGL arbitration and dispute provides us with additional confidence by taking out one of the larger risk elements from the overall legacy project cohort. And then number two the completion on the projects is now much more in sight than it's been at any period prior. And what we've done is we've analyzed a variety of factors and what could lead to the $125 million would be additional cost creep on the construction and development. And then with [Technical Difficulty] schedule that being said given the status that we have on these projects today, we remain confident the $110 million is appropriate. That being said we just want to provide stakeholders with a bit of a perspective around what financial risks could look like if schedule costs et cetera started creeping to the right and where we see appropriate risk bounds in association with that.

Yuri Lynk: Okay. And just as a follow-up. In terms of potential timing of realizing some of that $125 million, I mean, I would assume Q3 is going to be a clean quarter. But fair to say, it would be appropriate to kind of think about maybe a quarter or one-third of that getting recognized in the fourth quarter. How do we think about the timing and the likelihood?

Jerome Julier: Yeah. Good question, Yuri. So without confirming or denying any of your assumptions, the way that we would see the potential financial -- additional financial risks materialize if any would likely manifest themselves in association with any potential schedule slippage on the delivery of the projects and attainment of substantial completion. And to that end as we've noted, end of 2024, early 2025 is likely the area where we'll have better information in association with this. And so if we're thinking about where these costs could materialize and these are just estimates at these points, so we're not going to give ourselves any finality on this because these are potential impacts if any. But this idea of that a portion manifesting itself in the current fiscal year is possible and that the weighting that you noted is not a terrible way to think about it because it associates pretty much with 2024-2025, 2025 and probably not a bad way to think about it.

Yuri Lynk: Okay. Thanks for taking my questions.

Jerome Julier: Thanks, Yuri.

Operator: One moment for our next question. Our next question comes from Chris Murray with ATB Capital Markets. Your line is open.

Chris Murray: Yeah. Just maybe turning back a little bit looking at the concessions business for a second. If we sort of back out the $5.9 million one-time recoveries, you're kind of running call it maybe plus or minus $20 million in EBITDA. Just trying to think about how we should be thinking about the concessions business as a contribution on a go-forward basis? And I guess part of this is how are you seeing the stability of the airport right now? And is there anything else to be thinking about in terms of some of the other contracts that are underway changing that earnings profile over the next call it 18 months to 24 months?

Jerome Julier: Good question. So I'll break it down in a couple of ways. So with regards to the operating profit of the concessions business, in the quarter, we delivered $5 million versus roughly $9 million in the same quarter last year. I've switched to from EBITDA to operating profit on an as-adjusted basis Chris. The main difference there is largely related to reduction in development fees and increased pursuit costs. When projects are in active construction, there is a development fee or a fee that's collected by the concessions group and that can be additive to their earnings profile. And then with regards to the Bermuda airport, maybe I'll turn it over to Adam just to provide a little bit of context on the operating factors there.

Adam Borgatti: Sure. Thanks Jerome. So Bermuda continues to recover from its pre-pandemic traffic levels slowly. We're up to about the low 80% in terms of passenger volume that was experienced prior to COVID-19 impacts. But the key factor there is obviously the ability to have your revenues and associated costs for airlines and passengers, et cetera, increase at a level that exceeds your passenger volume. So from a financial perspective, the airport is operating well and in line with where we were before this despite lower passenger volume to kind of stay around this level or a small increase over time as hotel and other accommodation capacity increases in the market. To Jerome's point we've got -- where concessions is now as these major projects come off and the concessionaire moves into its O&M phases for the various LRTs et cetera you'll see some of that concessions' EBITDA reduced as the -- no longer carrying the -- but then there are opportunities moving forward as well as things do come on from construction into operations such as the Oneida battery storage project and is successful moving forward on the USVI opportunity. So a few puts and takes there in terms of timing but that's basically the dynamics that's driving concessions now.

Chris Murray: Okay I'll leave it there. Maybe turning back to the $125 million. So, I guess, under the accounting rules you book the $110 million because that's your kind of agreed to booked-up number. But thinking about the $125 million, I mean, outside of some schedule slippage and probably some recognition of that schedule slippage as you actually get closer to those target completion dates is there anything else? I guess what I'm trying to figure out is how to risk that $125 million materializing and how you're thinking about either certain events material costs, labor anything like that that could be driving kind of that $125 million number?

Jerome Julier: Yes. I mean, Chris, that's a good question. We're going to be limited in the amount of insight and perspective that we can really drill into for a variety of reasons. What I'll say is the $125 million was developed through a very detailed analysis of multiple variables outcomes across the full spectrum of activities involved with these projects whether it's schedule cost, claims, systems integration, training, et cetera, right? So I'd say, the complexity that underlies that figure is quite deep. And so we're not going to be able to point to any specific particular factor. And we're going to be pretty much sticking to the fact that there's the potential for additional financial risks if any being up to the $125 million. So that's -- here's the kind of standard deviation associated with that. We're just going to give the one up two point estimate.

Chris Murray: Okay. So maybe a different way to frame it. So like the $125 million really represents the worst case scenario in your best estimation?

Jerome Julier: It represents the potential for future additional risks to Aecon through the completion of the remaining construction right as of today based on what we know and the information we have available to us, right? Again just to reinforce the point where we stand today is $110 million and that's it. And then if those assumptions change based on what we see today, that's the additional -- future additional risk that could come into us.

Chris Murray: All right. Thanks. I'll leave it there.

Operator: Our next question comes from Benoit Poirier with Desjardins Capital Markets. Your line is open.

Benoit Poirier: Yes, thank you very much and good morning everyone. Just on the nuclear side could you maybe provide more color about the bidding opportunities right now and kind of the opportunity to scale up the work outside Canada?

Jean-Louis Servranckx: Yes Benoit. Thank you for the question. Aecon is ideally positioned for the future of nuclear. On one side we have all the refurbishment programs. I mean in Ontario the execution goes quite well. We are finalizing the two large reactors in Darlington. We have now acquired most of the units at Bruce only. The three last steam generators are still in the discussion but we have preferred arrangements on this one. Pickering now in terms of major rehabilitation is under negotiation with OPG for the four next units. It fits perfectly with the [indiscernible] of Darlington in terms of load of work for our people and our means of production. So this rehabilitation is quite strong. SMR I mean in Darlington the development phase is perfectly on track. We are all working hard in our alliance with GE Hitachi (OTC:HTHIY) and AtkinsRealis. I remind you that there is room here not only for one but for three additional. As I've told you a few months ago SMR is very interesting for us because it is a door to a lot of potential activities within Canada in other province or outside Canada. I mean you have probably noticed that we signed a cooperation agreement in Poland a few weeks ago. And that's just the beginning and we are very happy about it. In addition to this, we are ramping up in United States. You remember that in 2018 we made the acquisition of a small specialized nuclear welding company called [Indiscernible]. That's ramping up quite well. I mean we are now working on some refurbishment program for example for Dominion job of around $200 million but also on Savannah River I mean for the federal authorities. All these goes into the right direction. We have opened an office in Charlotte a few months ago. So, we are ideally positioned extremely happy on the way. We are learning. We are capitalizing on our experience and the position that we have in this nuclear field.

Benoit Poirier: That's great color. And when we look Jerome at the free cash flow generation and working cap there's been a great reversal in Q2. Could you provide maybe some granularity or greater detail about how we should expect the working cap and free cash flow to play out in the back half and for the full year?

Alistair MacCallum: Hey Benoit it's Alistair. So, as you know typically our business ramps up in terms of revenue in Q3 and Q4. So, from a working cap perspective we'd expect a build in Q3 as we typically have. And then Q4 tends to have a strong release of working capital. So, we'd expect that trend to continue. And I think as you said we've had a good release so far of working capital. We expect to have positive working capital at the end of the year. As you know our working capital can be lumpy depending on payments. And so I think a strong expectation that we'll be positive from a working capital perspective at the end of the year.

Benoit Poirier: Okay. Thank you.

Jerome Julier: Benoit, just layering on it also just from a cash flow perspective [Technical Difficulty] we made the acquisition of Powerline. So that needs to be factored in. And then as well the NCIB needs to be factored in as well.

Benoit Poirier: Okay. That's great. And with respect to the acquisition of Xtreme Powerline, how should we be thinking about the integration and whether your willingness to do more? Are you going to take a pause and digest or still looking to beef up your presence in the utility segment?

Jean-Louis Servranckx: Okay. I will take on this one, Benoit. We're extremely happy with the acquisition of Xtreme. It's perfectly within the target. It's perfectly within our core competency. It's in Michigan, which means quite close from us. It's a very professional company with more than 300 employees, in United States. The fact to have your own employees professionally trained and loyal to the company is extremely important. You remember what I said last time? I mean our strategy is to try to make acquisition in the mid-single digit in terms of multiplier for the EBITDA and integrate them within our Aecon Utilities Group, which have been valued between nine and ten times multiplier. This is what we have been doing. It's a very strong company. So of course we have to integrate this company within Aecon. We are rather optimistic. I mean we had very thorough due diligence. We know that the DNA is the same. We know that the teams can work together. What is important are, the very strong relation with DTE, but also the agility of this company to work in addition to their core business on all the emergency response happening within the United States. And this is quite important. I mean its part of the business that is more-and-more important. I mean you probably noticed in our introduction that we spoke about Saint Vincent and the hurricane, I mean, Beryl in Caribbean. So it's not usual to have a Category 5 hurricane in June in Caribbean, but we were ready for this. Impacts have been minor, just a few weeks less than $2 million of losses, no fatalities. No wounded people within our team. I mean there will be quite a large trend of investment in all those emergency response due to climate change. Xtreme is very well positioned for this. So we are happy about it. We're going to integrate it and we will progress forward. We are rather ambitious although prudent on our growth in United States and International.

Benoit Poirier: That's great color. Thank you, Jean-Louis.

Operator: One moment for our next question. Our next question comes from Ian Gillies with Stifel. Your line is open.

Ian Gillies: Morning everyone.

Jean-Louis Servranckx: Morning.

Jerome Julier: Good morning.

Ian Gillies: You've quantified the risk for the remaining three projects obviously through the end of 2025. Could you maybe qualitatively address what sort of risks or opportunities you may see on those projects for recovery, maybe in 2026 just as you get post-project completion there's true-ups, et cetera?

Jean-Louis Servranckx: Yes. I can speak a little about this, and maybe Jerome if you want to add something. I mean these are extremely complex projects with a lot of interfaces, with a lot of stakeholders. And we consider, I mean, at least of the two LRTs that there has been major modification in the condition of executions of our contract due to these interferences. So, we will have a strong focus on recovering what we think is fair due to the consequences of those interfaces. And I would say, we do it with a lot of strength, because we just consider that this is what has to be done in line with the project agreement that we have been signing quite a number of years ago. It means that we will fight up to the end so that our rights are recognized, and that we just receive fair and honorable compensation for the issue that we have been facing. And this is very important. So, first of all, substantial completion very important. I mean as soon as possible getting substantially completed on this job and going to the next phase, which is maintenance under our contract, but also recovering with a lot of energy any amounts of money that we are convinced are due to our companies. Jerome, do you want to add something?

Jerome Julier: I think it was well articulated Jean-Louis. Ian, just to your point, these would be circumstances that could take a notable amount of time to resolve and move through the various resolution methods. And so, I think from our perspective qualitatively, Jean-Louis said it well. And just from a timing standpoint, it's probably -- we're not forecasting any pluses or minuses just to the extent that it's so far out at this point. But it's, obviously, a keen focus for the team.

Ian Gillies: Understood. As you look across your customers today and ongoing bid activity, are there any notable pockets of weakness that you're seeing on the private capital side? There's some stuff that seems to be coming up in the US. But in Canada, is there any cause for concern at this point?

Jerome Julier: Look, one of the benefits of the diversified business profile is, it allows us when there's a little bit of chop in the water, we can still navigate it pretty readily. One area that we did call out was just with regards to the utilities business. We have noticed maybe a little bit less robust dynamic in association with telecommunications and natural gas distribution. I think that's likely temporal, like it's something that will pass, but it's something that we -- the work will need to get done. But we just view it as probably just moving a little bit to the right. I don't know Jean-Louis, if there's any other areas that you see strength or weaknesses on the Canadian side.

Jean-Louis Servranckx: No. What we can see that probably United States is more in advance than Canada on everything related with energy transition, all the subsidizing program and everything to make it happen quickly. Especially I mean this is why Xtreme was such an important acquisition I mean through the Bipartisan Act and the Inflation Reduction Act. I mean there's more than $65 billion already dedicated and ready to go just to modernize the nation and electrical infrastructure. So we just think that United States is in advance. But Canada, I mean is not in a standstill. So we are also rather optimistic on this.

Ian Gillies: Perfect. I'll it there. Thank you very much.

Operator: [Operator Instructions] One moment for our next question. Our next question comes from Sean Jack with Raymond James. Your line is open.

Sean Jack: Good morning guys. Thanks for taking my question. Just a quick question on Xtreme. Wondering if you could comment on how competitive that auction process was and also wondering, if you're seeing dynamics for auction processes getting a bit easier or harder since you began looking.

Jerome Julier: Thanks, Sean, yes, no great question. This was a unique one for us. We actually really liked the firm as did Oaktree in its review of opportunities prior to our transaction in the fall of last year. So it was actually a nice one for us when we came together to [Technical Difficulty]. We're really trying to avoid big auctions, big headline numbers, those that would compete with lots of financial capital for platform investments. It's not what we need. It's not what we and our partner feel is the right approach for this business. And so we're going to be very prudent and judicious with our capital. Seek out as Jean-Louis described fair value [Technical Difficulty] companies ones that will integrate well culturally with a safety-focused culture and what we describe as our land-and-expand strategy which is find great businesses that do few things very well for great clients and then apply what we can also bring which is additional capabilities more work into Aecon and the ability to take on larger and more complex projects to our balance sheet and credit capacity. So very successful outcome. We had lots of time and the right approach on due diligence for this one and intend to do the same going forward on a very measured approach and lots more in the funnel right now that we think is in our wheelhouse.

Sean Jack: Okay. Perfect. And last one just for Xtreme specifically. Wondering if there's any puts and takes on seasonality that you guys would want to call out or does it pretty well match Aecon's construction business?

Jerome Julier: Yes. It's got similar levels to our seasonality. Again, lots of its work is in the north of the US adjacent to our border. And so you'd have the same weather impacts on outdoor work that we would have in our utilities. So aside from as Jean-Louis described storm response and emergency services that would move elsewhere throughout the US potentially expanding off-peak times. It mostly follows our seasonal pattern.

Sean Jack: Okay. Perfect. Appreciate it. Thanks, guy.

Jerome Julier: Thanks, Sean.

Operator: And I'm not showing any further questions at this time. I'd like to turn the call back over to Adam for any closing remarks.

Adam Borgatti: Great. Thanks, Kevin and thanks everyone for your participation today. As always, feel free to reach out to us with further questions and comments. We welcome the feedback and wish you a good rest of the day. And we'll speak with you on the next call.

Operator: Ladies and gentlemen, this does conclude today's presentation. You may now disconnect and have a wonderful day.

This article was generated with the support of AI and reviewed by an editor. For more information see our T&C.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.