EQM sees WV-VA Mountain Valley natgas pipe completed in 4th qtr 2019

Published 2018-11-28, 01:17 p/m
© Reuters.  EQM sees WV-VA Mountain Valley natgas pipe completed in 4th qtr 2019
ED
-
NG
-
NEE
-
RGCO
-
ALA
-

Nov 28 (Reuters) - EQM Midstream Partners LP EQM.N said on Wednesday it still expected to complete the $4.6 billion Mountain Valley natural gas pipeline from West Virginia to Virginia in the fourth quarter of 2019 despite a legal opinion explaining why an appeals court vacated a water permit for the project.

The U.S. Court of Appeals for the Fourth Circuit issued the opinion late Tuesday explaining why it sided with environmental groups in October and decided to vacate the so-called Nationwide Permit 12 that allows the pipeline to cross rivers in West Virginia.

In the opinion, the court said the project's proposed construction methods violated a special condition put forward by West Virginia, requiring stream crossings to be completed within 72 hours.

The court also pointed to another special condition requiring projects to obtain state water quality certification for pipelines bigger than 36 inches (91.4 centimeters) in diameter. Mountain Valley has a 42-inch pipeline.

West Virginia is in the process of modifying the special conditions to allow Mountain Valley and another gas pipe, Dominion Energy Inc's D.N Atlantic Coast, to move forward. at Height Capital Markets in Washington said they expect West Virginia's Department of Environmental Protection to issue the modified special conditions by the end of year, allowing Mountain Valley to seek a new permit from the Army Corps.

"If all agencies move quickly, Mountain Valley could have all permits reinstated by mid-2019, leaving just enough time to finish the project by the end of 2019," analysts at Height Capital Markets said in a report.

Mountain Valley is one of several pipelines under construction to connect growing output in the Marcellus and Utica shale basins in Pennsylvania, West Virginia and Ohio with customers in other parts of the United States and Canada. EQM started construction in February, it originally estimated the project would cost about $3.5 billion and be completed by the end of 2018. 303-mile (488-kilometer) pipeline is designed to deliver 2 billion cubic feet per day of gas to meet growing demand for the fuel for power generation and other uses in the U.S. Southeast and Mid-Atlantic.

One billion cubic feet is enough gas to supply about 5 million U.S. homes for a day.

Mountain Valley is owned by units of EQM, NextEra Energy Inc (NYSE:NEE) NEE.N , Consolidated Edison Inc (NYSE:ED) ED.N , AlatGas Ltd ALA.TO and RGC Resources Inc RGCO.O . EQM will operate the pipeline and owns a significant interest in the venture.

<^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ U.S. court sets Sept. hearing for EQT Mountain Valley natgas pipeline

FACTBOX-U.S. new natural gas pipeline projects

EQT Midstream to Expand Mountain Valley Pipeline to South

UPDATE 1-EQT delays W.V.-Va. Mountain Valley natgas pipe completion to Q1

UPDATE 1-U.S. court vacates two permits for EQT Mountain Valley gas pipeline

Army Corps asks court to lift W.Virginia Mountain Valley natgas pipe stay

Mountain Valley Pipeline Revises Cost Estimate

Dominion to complete WV-NC Atlantic Coast natgas pipe in mid 2020

EQT does not expect US court order to hold up Mountain Valley natgas pipe

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.