June 13 (Reuters) - Suncor Energy Inc SU.TO
* Suncor Energy provides update on Syncrude Mildred Lake Oil sands facility
* Shipments have been reduced to approximately 130 kbpd in order to complete accelerated maintenance
* Says there is no change to Suncor's overall production guidance for 2017.
* Repairs are progressing as planned, maintenance work scheduled for fall has been added to plan, extending timing of full ramp up to mid-July Source text for Eikon: Further company coverage: SU.TO