March 21 (Reuters) - RMP Energy Inc RMP.TO
* RMP Energy provides operations update highlighting Elmworth delineation success, updates market guidance and reports year-end reserves and fiscal 2016 financial results
* Says RMP expects to have 13-30 well tied into company-owned infrastructure and placed on-production later this week
* Says in addition to 13-30 well, co is budgeted to drill three more (3.0 net) montney horizontal wells at Waskahigan this year
* For 2017, company is budgeting to incur $49 million in exploration and development capital expenditures
* For second half of 2017, company is forecasting production to average approximately 4,500 boe/d Source text for Eikon: ID:nCCN4rtrHh Further company coverage: RMP.TO