Feb 28 (Reuters) - Amerigo Resources Ltd ARG.TO :
* AMERIGO PROVIDES UPDATE ON Q1-2019 PRODUCTION
* AMERIGO RESOURCES LTD - MVC RECEIVED A NOTIFICATION FROM DEPARTMENT OF DAMS, TAILINGS AND HYDRAULIC RESOURCES OF CODELCO'S DIVISIÓN EL TENIENTE
* AMERIGO RESOURCES LTD - NOTIFICATION ADVISED A SHUTDOWN OF DET'S TAILINGS SYSTEM DURING A 144-HOUR PERIOD FROM MARCH 10 TO MARCH 16, 2019 INCLUSIVE
* AMERIGO RESOURCES LTD - DET WILL BE CONDUCTING MAINTENANCE WORK IN VARIOUS SECTIONS OF ENTIRE DET TAILINGS CONCRETE CHANNEL DURING THIS PERIOD.
* AMERIGO RESOURCES LTD - DET WILL SUSPEND FLOW OF FRESH TAILINGS TO MVC'S PLANT AND MVC WILL BE REQUIRED TO SUSPEND PRODUCTION FROM CAUQUENES
* AMERIGO RESOURCES LTD - MVC WILL REQUIRE AN ADDITIONAL DAY OF SUSPENDED OPERATIONS, FOR A TOTAL ESTIMATED SUSPENSION OF 7 DAYS TO RESTART EQUIPMENT
* AMERIGO RESOURCES LTD - SUSPENSION OF PRODUCTION FROM MVC DURING MAINTENANCE PERIOD WILL FURTHER AFFECT Q1-2019 PRODUCTION
* AMERIGO RESOURCES LTD - AMERIGO CURRENTLY ESTIMATES Q1-2019 PRODUCTION OF 13.5 MILLION POUNDS OF COPPER
* AMERIGO RESOURCES LTD - AMERIGO WILL REVIEW WITH MVC POTENTIAL CHANGES TO PRODUCTION PLAN FOR Q2, Q3 AND Q4 OF 2019