March 3 (Reuters) - Dundee Precious Metals Inc DPM.TO :
* DUNDEE PRECIOUS METALS - SHUTDOWN AT TSUMEB SMELTER IN NAMIBIA NOW EXPECTED TO EXTEND FOR UP TO 40 DAYS, RETURN TO FULL OPERATIONS TARGETED FOR MARCH END
* DUNDEE PRECIOUS METALS - PROCESSING OF COMPLEX CONCENTRATE FROM CO'S CHELOPECH MINE IS NOT EXPECTED TO BE IMPACTED BY AUSMELT FURNACE MAINTENANCE
* DUNDEE PRECIOUS METALS INC - EXTENDED TIMELINE IS NOT EXPECTED TO IMPACT 2021 GUIDANCE FOR COMPLEX CONCENTRATE SMELTED OF 220,000 AND 250,000 TONNES
* DUNDEE PRECIOUS METALS - EXTENDED TIMELINE IS NOT EXPECTED TO IMPACT TSUMEB'S FORECAST 2021 SUSTAINING CAPITAL EXPENDITURES OF $16 TO $20 MILLION