April 24 (Reuters) - Hudson Resources Inc HUD.V :
* HUDSON RESOURCES PROVIDES UPDATE ON THE PROCESS PLANT RAMP UP AT THE WHITE MOUNTAIN ANORTHOSITE MINE
* HUDSON RESOURCES INC - WHITE MOUNTAIN PROCESS PLANT RAMP UP HAS ACHIEVED 50% CAPACITY AND PRODUCTION CONTINUES TO INCREASE
* HUDSON RESOURCES INC - ENCOUNTERED SOME PRODUCTION ISSUES ASSOCIATED WITH EXTREMELY COLD TEMPERATURES IN FEBRUARY AND MARCH
* HUDSON RESOURCES - WILL INSTALL A HEATER SYSTEM THIS SUMMER TO MANAGE PRODUCTION ISSUES ASSOCIATED WITH EXTREMELY COLD TEMPERATURES FOR NEXT WINTER
* HUDSON RESOURCES INC - COLD TEMPERATURE IS CURRENTLY NOT AN ISSUE FOR PLANT OPERATIONS.
* HUDSON RESOURCES INC - AT CURRENT OPERATING PARAMETERS, WE ARE ON TRACK TO MEET OUR SHIPMENT TARGETS FOR THIS YEAR